NetSuite Sync Error | You cannot make changes to this period without the Allow Non-G/L Changes permission.
If you are paying with a Vendor Credit, confirm whether the credit is in a locked period. If it is, that is the reason for the error.
To resolve:
- Option 1 (Recommended):
- Manually record the payment in NetSuite .
- Click the "Open in NetSuite" hyperlink and then click "Make Payment" .
- Copy the Ramp Bill URL and paste it into the ramp_receipt_url field in NetSuite.
- Select the Bill and associated Vendor Credit(s) .
- Click Save .
- Option 2:
- Navigate to NetSuite > Setup > Accounting > Manage Accounting Period .
- Locate the locked period and temporarily unlock it.
- Navigate back to Ramp and retry the sync.
- Once synced, return to NetSuite and lock the period again.
This is a current limitation. The Ramp team is working on a solution to prevent this error in the future.